Germantown Park Stormwater Management and Stream Restoration Project (Phase I)

Project Highlight

As a part of the County's effort to protect our waters, eight stormwater ponds and a section of stream within the Germantown Park community were selected for restoration to help reduce stormwater pollution draining into our streams. Four of the eight stormwater ponds will be included in this phase of the project. The other four stormwater ponds and the stream section are part of the second phase - Germantown Park Stormwater Management and Stream Restoration Project (Phase II).

Various public events will be held throughout the project phases for residents to learn about the project and to provide input on the design of the project. Public events and project schedules may vary by site. Click on each site tab on the right for more specific information.

 

PROJECT FACTS
Project Status: In Design / Construction Pending
Total Drainage Area: 54 Acres
Total Percent Impervious: 36%
Total Stream Project Length: 0 in Phase I
Estimated Cost: $1.5 million
Monitoring: Yes
Watershed: Seneca Creek (Gunners Branch Tributary)
Contact: Doug Marshall
Email: Douglas.Marshall@montgomerycountymd.gov
Phone: (240) 777-7767

 

Germantown Park Stormwater Facility Retrofits Factsheet (PDF, 464 KB)

 

 

Sites: 10917 - Pond 10985 - Pond 11161 - Pond 11156 - Pond
Site Status: In Design In Design Construction Pending In Design
Site Drainage Area: 15.2Ac 1.8Ac 27.2Ac 9.9Ac
Percent Impervious (%): 39% 12% 36% 34%
Stream Project Length: ---------- ---------- ---------- ----------

*Information is subject to change

Image of Germantown Park Phase I

To download, click (PDF, 1.68 MB)

 

Germantown Park - North Pond (10917)

Stormwater Pond 10917 is located between Sage Way and Bay Leaf Way, and discharges into Pond 10985 to the south.

 

Image of Cinnamon Woods North Pond

 

 

Public Events and Site Schedule
Event Date / Time Location
Survey and Site Analysis Spring 2013  
Preliminary Site Assessment Summer 2013  
Public Meeting July 18, 2013 / 7:30 p.m. Germantown Park Community Center 18400 Cinnamon Dr. Germantown, MD 20874
Concept Design Plans Spring 2014  
Community Walk TBD TBD
Final Plans Winter 2015  
Construction Fall 2016  

 

Image of Asset 10917

To download, click (PDF, 313 KB)

 

 

Document and Design Plans
July 2013 Public Meeting Presentation (PDF, 2.35 MB) (Archive)
  Public Meeting Flyer (PDF, 509 KB) (Archive)

 

Germantown Park - South Pond (10985)

Stormwater Pond 10985 is located below Pond 10917 between Sage Ter and Bay Leaf Way, and recieves flow from Pond 10917 to the north.

 

Image of South Pond Asset 10985

 

 

Public Events and Site Schedule
Event Date / Time Location
Survey and Site Analysis Spring 2013  
Preliminary Site Assessment Summer 2013  
Public Meeting July 18, 2013 / 7:30 p.m. Germantown Park Community Center 18400 Cinnamon Dr. Germantown, MD 20874
Concept Design Plans Spring 2014  
Community Walk TBD TBD
Final Plans Winter 2015  
Construction Fall 2016  

 

Image of Asset 10985

To download, click (PDF, 315 KB)

 

Document and Design Plans
July 2013 Public Meeting Presentation (PDF, 2.35 MB) (Archive)
  Public Meeting Flyer (PDF, 509 KB) (Archive)

 

Germantown Park - Pond 11156

Stormwater Pond 11156 is located adjacent to Red Pepper Ct.

Image of Asset 11156

 

 

Public Events and Site Schedule
Event Date / Time Location
Survey and Site Analysis Spring 2013  
Preliminary Site Assessment Summer 2013  
Public Meeting July 18, 2013 / 7:30 p.m. Germantown Park Community Center 18400 Cinnamon Dr. Germantown, MD 20874
Concept Design Plans Spring 2014  
Community Walk TBD TBD
Final Plans Winter 2015  
Construction Fall 2016  

 

Image of Asset 11156

To download, click (PDF, 354 KB)

 

Document and Design Plans
July 2013 Public Meeting Presentation (PDF, 2.35 MB) (Archive)
  Public Meeting Flyer (PDF, 509 KB) (Archive)

 

Germantown Park - Pond 11161

Stormwater Pond 11161 is located between Mustard Seed Ct. and Sage Ter.

 

Image of Asset 11161

 

 

Public Events and Site Schedule
Event Date / Time Location
Survey and Site Analysis Spring 2013  
Preliminary Site Assessment Summer 2013  
Public Meeting July 18, 2013 / 7:30 p.m. Germantown Park Community Center 18400 Cinnamon Dr. Germantown, MD 20874
Concept Design Plans Spring 2014  
Community Walk TBD TBD
Final Plans Spring 2015  
Construction Began October 2015. Expected Completion June 2016.  

 

Image of Asset 11161

To download, click (PDF, 335 KB)

Document and Design Plans
July 2013 Public Meeting Presentation (PDF, 2.35 MB) (Archive)
  Public Meeting Flyer (PDF, 509 KB) (Archive)