Mill Creek South Stormwater Pond

 

As a part of the County's effort in protecting our waters, the stormwater pond within the Mill Creek community was selected for upgrade to help reduce stormwater pollution draining into our streams.

Various public events will be held through out the project phases for residents to learn about the project and to provide input on the design of the project. Check out the Project Schedule at the bottom of the page for more information!

                                

 

PROJECT FACTS
Project Status: In Design
Total Drainage Area: 588 Ac
Total Percent Impervious: 21%
Total Stream Project Length: N/A
Estimated Cost: $830,000
Monitoring: No
Watershed: Rock Creek
Contact: Joan Fernandez
Email: Joan.Fernandez@montgomerycountymd.gov
Phone: (240) 499-8531

     *Information is subject to change

    Image of Mill Creek Stormwater Pond

     To download, click (PDF, 1.47 MB)

 

Public Events and Site Schedule
Event  Date / Time Location
Survey and Site Analysis Completed Fall 2013  
Preliminary Site Assessment Completed Fall 2013  
Public Meeting TBD TBD
Concept Design Plans Winter 2014  
Community Walk Spring 2015  
Final Plans Summer/Fall 2015  
Construction Winter 2015  

*Project schedule is tentative and dates are subject to change.