Skip Navigation

Wheaton Woods I Green Streets

As a part of the County's effort to protect our waters, the Wheaton Woods neighborhood was selected for a Green Street project to help reduce stormwater pollution that drains into our streams. Green Street projects generally involve installing small-scale stormwater practices within the county's right-of-way to capture water from roadways and sidewalks during storms.

Residents within the Wheaton Woods project area can also help reduce stormwater pollution by installing stormwater practices on their property through the county's targeted RainScapes Neighborhood program.

Various public events will be held throughout the project phases for residents to learn about the project and to provide input on the design of the project. Check out the Project Schedule at the bottom of the page for more information!

 

                               

 

PROJECT FACTS
Project Status: In Design
Total Drainage Area: 264.7 Ac
Total Percent Impervious: 34%
Total Stream Project Length: N/A
Estimated Cost: $1,536,313.00
Monitoring: No
Watershed: Rock Creek
Contact: Christy Ciarametaro
Email: Christy.Ciarametaro@montgomerycountymd.gov
Phone: (240) 777-7720

      *Information is subject to change

     Image of Wheaton Woods I Green Streets

      To download, click (PDF, 1.06 MB)

 

Project Schedule and Documents

 

Public Events and Site Schedule
Event Date / Time  Location
Survey and Site Analysis Spring 2013  
Preliminary Site Assessment  August 2013  
Public Meeting March 25, 2014, 7:00-8:30pm Aspen Hill Library, 4407 Aspen Hill Rd., Rockville, MD 20853
Draft Designs Summer / Fall 2014  
Community Walk Winter 2014  
Final Plans Spring 2015  
Construction Fall 2015  

*Project schedule is tentative and dates are subject to change.

 

Document and Design Plans
March 2014 Wheaton Woods Factsheet (PDF, 1.14MB)
  Wheaton Woods Preliminary Assessment Maps (PDF, 19.8MB)
  Wheaton Woods Presentation (PDF, 7.2MB)
  Green Streets Poster