Longmead Crossing Stormwater Project As a part of the County's effort to protect our waters, the stormwater pond within the Longmead Crossing community was selected for upgrade and improvements to bring the pond into compliance with current safety and performance standards to reduce the impacts of stormwater runoff on our streams and the Chesapeake Bay.

Upgrades and improvements to the stormwater management pond will include: regrading the pond to increase water storage capacity, installing a new 48 inch concrete spillway pipe through the dam, replacing the riser structure, reconstructing the dam and planting trees, shrubs and aquatic plants around the perimeter of the pond.
View more pictures of the project >>

Project Details

Image of Old Farm Creek Restoration

Public Events and Project Schedule

Calendar Graphic

Survey and Site Analysis

Spring 2013

Calendar Graphic

Preliminary Site Assessment

Summer 2013

Calendar Graphic

Public Meeting

February 2014
Longmead Crossing

Calendar Graphic

Concept Design Plans

Summer 2014

Calendar Graphic

Final Plans

June 2023

Calendar Graphic

Construction

June 2024 - March 2025