Survey and Site Analysis

Winter/Spring 2015

Calendar Graphic

Preliminary Site Assessment

Spring 2015

Calendar Graphic

Concept Design Plans   

Fall 2016
 

Calendar Graphic

Public Meeting

1/23/18 @ 7pm at Whetstone Elementary School - All Purpose Room
19201 Thomas Farm Road, Gaithersburg, MD  20879

Calendar Graphic

Final Plans

Winter 2018 / Spring 2019

Calendar Graphic

Construction

Spring/Summer 2019

*Project schedule is tentative and dates are subject to change.

 

 
 
 
 