WATER SUPPLY STUDY - APPENDIX D
TIMELINE FOR IMPLEMENTATION
ID | Task Name | Duration | Start | Finish |
---|---|---|---|---|
1 | Residential Sprinkler Legislation | 520 days | Mon 7/3/00 | Fri 6/28/02 |
2 | Additional Tankers and Tanker Pumpers | 260 days | Mon 7/2/01 | Fri 6/28/02 |
3 | Additional Tankers and Tanker Pumpers | 260 days | Wed 7/3/02 | Tue 7/1/03 |
4 | Additional Tankers and Tanker Pumpers | 260 days | Wed 7/2/03 | Tue 6/29/04 |
5 | Additional Tankers and Tanker Pumpers | 260 days | Thu 7/1/04 | Wed 6/29/05 |
6 | Additional Tankers and Tanker Pumpers | 260 days | Fri 7/1/05 | Thu 6/29/06 |
7 | Service Testing of Pumpers | 2607 days | Mon 7/3/00 | Tue 6/29/10 |
8 | Conversion to 4" hose | 1304 days | Mon 7/3/00 | Thu 6/30/05 |
9 | Hose Testing Requirement | 2607 days | Mon 7/3/00 | Tue 6/29/10 |
10 | Purchase 1500 gpm Pumpers | 2607 days | Mon 7/3/00 | Tue 6/29/10 |
11 | Standardization of Hose Compliment | 1560 days | Mon 7/3/00 | Fri 6/23/06 |
12 | Tanker Specification and Review | 520 days | Mon 7/3/00 | Fri 6/28/02 |
13 | Installation of Dry Vertical Standpipe- Limited Access Hgwys |
2607 days | Mon 7/3/00 | Tue 6/29/10 |
14 | Pilot test of CAFS | 520 days | Mon 7/2/01 | Fri 6/27/03 |
15 | Flow Requirement, 500 gpm for 10 min |
2607 days | Mon 7/3/00 | Tue 6/29/10 |
16 | MCFRS Policy- Water Supply Operations & Training |
520 days | Mon 7/3/00 | Fri 6/28/02 |
17 | Assign Tankers to non-hydranted areas | 130 days | Mon 7/3/00 | Fri 12/29/00 |
18 | Flow requirement, 3000 gpm to multi-family residential | 130 days | Mon 7/3/00 | Fri 12/29/00 |
19 | Identify- ISO Certified Drafting Points | 2607 days | Mon 7/3/00 | Tue 6/29/10 |
20 | Water Supply Task Force | 390 days | Mon 7/3/00 | Fri 12/28/01 |
21 | Sound Barrier- FD Connections | 2607 days | Mon 7/3/00 | Tue 6/29/10 |
22 | Sinage - Alternate Water Supply | 2607 days | Mon 7/3/00 | Tue 6/29/10 |
23 | Tactical Operations- Dry Vertical Standpipe |
260 days | Mon 7/3/00 | Fri 6/29/01 |
24 | Pilot - Hydrant Marking Systems | 260 days | Wed 7/3/02 | Tue 7/1/03 |
25 | Standardized GIS Maps for Water Supply |
1040 days | Mon 7/3/00 | Fri 6/25/04 |
26 | Inspection Procedures: Buildings with water based systems |
520 days | Mon 7/3/00 | Fri 6/28/02 |
27 | Contingency Plan- Catastrophic Failure of Water Supply |
520 days | Mon 7/3/00 | Fri 6/28/02 |
28 | Dry Hydrant Program | 2607 days | Mon 7/3/00 | Tue 6/29/10 |
29 | Class B Foam Strategy | 778 days | Mon 7/3/00 | Wed 6/25/03 |
30 | Risk Analysis by Station Response Area | 520 days | Mon 7/3/00 | Fri 6/28/02 |
31 | Improve Automated Incident Reporting | 260 days | Mon 7/3/00 | Fri 6/29/01 |
32 | Water Main Looping, Increased Storage - WSSC High Zone | 2607 days | Mon 7/3/00 | Tue 6/29/10 |
33 | Improve relationship with water authorities | 2607 days | Mon 7/3/00 | Tue 6/29/10 |
34 | Coordination of hydrant flow information | 2607 days | Mon 7/3/00 | Tue 6/29/10 |
35 | Improve maintenance of WSSC hydrants | 2607 days | Mon 7/3/00 | Tue 6/29/10 |
36 | Address problems with dry standpipe - American Legion Bridge |
1304 days | Mon 7/3/00 | Thu 6/30/05 |