Gold Mine Road Bridge (M-0096)

This project provides for the replacement of the existing 33 foot single span bridge over Hawlings River.

For additional information please visit us on twitter at MC_DTE @MOCO_DTE #GoldMineRd

  • Construction: October 2018 – November 2019
  • Road closure of intersection at Chandlee Mill Road and Gold Mine Rd is schedule to be on early Summer 2019. There will be an additional detour plan set up at that time to provide an alternate route.
  • Gold Mine Road to reopen by late Summer 2019.
  • General work will continue to Fall of 2019 with possible flagging operations.

Bill Sittinger
Project Manager/ Construction Field Supervisor
MCDOT/DTE/Construction
100 Edison Park Drive, 4th Floor
Gaithersburg, Maryland 20878
Phone: 240-777-7272
E-mail: [email protected]

Area Map