Skip to main content

Click here to access previous calendar activities for Wheaton project.

Click here for Newsletter Archives (pdf)

Look Ahead - Week of February 17 to February 23, 2019

Project Status

The project remains on-schedule for a May 27, 2020 substantial completion.

Headliner

CONSTRUCTION OF FORTH FLOOR WELL UNDERWAY

SPECIAL NOTE: AN EXISTING WATERLINE IS LEAKING IN THE BED OF ENNALLS AVE. NEAR GRANDVIEW AVENUE. THE WSSC IS AWARE OF THIS AND THE PIPE WILL BE REPAIRED TUESDAY NIGHT 2/19.

Garage

Electrical work, block masonry, door frames, and sprinkler installation is underway at Levels P4 and P3. The piping in the garage is complete.

Office Building

First Floor

Concrete Complete

Second Floor

Concrete Complete

Third Floor

Concrete Complete

Fourth Floor

Concrete pours #1 and #2 completed. Pour #3, the final pour, is scheduled on Wednesday 2/20.

Fourth Floor

Photo showing typical floor construction - January 2019

Column Construction

Column construction nearly complete between the 4th and 5th floors.

Photo showing column pour between the second and third floors

Utility Construction

Pepco relocations are complete with exception of pole removal that will follow removal of the overhead Verizon lines.

Verizon Underground Work

Complete

Town Plaza

The Town Plaza will include an amphitheater, stage, lighting, art work, Wi-Fi, bio-retention areas, landscaping, and elevated walkways from the new Town Plaza to Georgia Ave (to the south) and to the WMATA tower connecting to the WMATA parking garage located on Veirs Mill Road.

Excavation and demolition of old building foundations, stairs, and walkways is nearing completion. All work associated with the Town Plaza is scheduled to be complete late- May 2020, at building completion.

Follow Project Progress via the Project Camera

A camera has been installed to view construction on the site. Click here to access the camera.

Upcoming and Ongoing Activities:

  • Place concrete 4th floor
  • Build columns 4th floor to 5th floor
  • Placement of concrete block, door frames, and electrical in the garage on Levels P4, P3, P2
  • Offside material fabrications
    • Stone
    • Windows
    • Building skin
    • Chillers HVAC
    • Interior lights
  • Repair waterline in Ennalls Drive
  • Install sewer connection from Grandview Ave to new building
  • Commence installation of sprinkler system in garage
  • Town Plaza (South of Reedie Drive)
    • Demolition of Concrete
    • Excavation and haul-off
    • Rough grading
Go Top