Wheaton Revitalization Project
Click here to access previous calendar activities for Wheaton project.
Click here for Newsletter Archives (pdf)
Click here for Wheaton project photos as of June 14, 2020.
Look Ahead – Week of June 28 to July 4, 2020
The project is holding steady at 99+-percent complete. As noted over the past two-months, the impacts of COVID-19 led to a revised Substantial Completion date that now stands at July 9, 2020.
This past week showed a fifth straight week of no confirmed or suspected COVID-19 on the site.
Punch list work is substantial complete. All efforts are now focused on project closeout that includes the closeout of numerous (>25 permits) with the Department of Permitting Services.
The COVID precautions employed by Clark Construction, (builder), Stonebridge Carras, (Developer), and O’Connell & Lawrence, Inc., has paid significant dividends as the project has gone five-consecutive weeks without a positive COVID test result.
Lot 13
Lot 13 is being rebuilt to restore the parking availability that was taken by the worksite. A new thoroughfare between Triangle Lane and Grandview is being created, new ADA compliant sidewalks are being built, new paving installed, meters will be removed, and a new revenue collection system will be installed.
This effort will double the surface-lot parking capacity over what existed during the past 37-months of construction.
Please expect intermittent closures of the Lot 13 as DOT undertakes this construction. All work related to this effort is expected to be completed by July 9, 2020.
Construction is complete and the project is in the closeout phase, except as noted below.
Move in will begin with 37-employees with the MNCPPC IT force beginning July 20 and completing by the end of July.
The balance of the moves for MNCPPC and Montgomery County departments is expected to start in late-July and continue through August.
Moving boxes are being distributed.
The building tenants include: