Flash on US 29 started service in October 2020. Learn more at RidetheFlash.com
Transit Project
US 29 Flash is in Phase 2:
Routes / Upcoming Projects:
The project is in the process of completing preliminary engineering (35% design) to develop the design of the recommended median bus lane hybrid concept.
Flash on US 29 started service in October 2020. Learn more at RidetheFlash.com.
Join our mailing list and receive project updates and community meetings and events.
Corridor Advisory Committees (CACs) were created in 2015 as part of the Montgomery County Department of Transportation’s (MCDOT) planned Bus Rapid Transit (BRT) service on US 29 from the Burtonsville to downtown Silver Spring. The committee is made up of residents, business owners, and other stakeholders along the corridor. The CAC meetings allow MCDOT to both give updates on the project to members of the community and to gather feedback from stakeholders along this portion of the corridor.
For more information on this corridor, see the Countywide Transit Corridors Functional Master Plan .
Meeting #1 - Corridor Advisory Committee (CAC) Meeting - Wednesday, April 24, 2024
Meeting #2 - Corridor Advisory Committee (CAC) Meeting - Thursday, January 30, 2025
Meeting #3 - Public Meeting - Tuesday, April 8, 2025
Meeting #4 - Corridor Advisory Committee (CAC) Meeting - Tuesday, June 3, 2025
Meeting #5 - Public Meeting - Tuesday, June 10, 2025
Luis Boezi Burnt Mills Hills Citizens Association Sharon Canavan Northwood Four Corners Civic Association Pat Connolly Holy Cross Health Ian Dewaal Interested Resident
Barbara (Bee) Ditzler League of Women Voters Brian Downie Saul Centers, Inc . Jay Elvove Montgomery County Civic Federation/North Hills of Sligo Creek Civic Association Avi Halpert United Therapeutics Corporation Kevin Harris Zen Renovations Stephanie Helsing Greater Silver Spring Chamber of Commerce John Holden South Four Corners Citizens Association
Joan Johnson Washington Area Bicyclist Association Matthew Koch Interested Resident Tom Lansworth Interested Resident Michael Larkin Action Committee for Transit Anita Morrison Indian Springs Civic Association Peter Myo Khin Tamarack Triangle Civic Association John Parrish Interested Resident Mark Posner Interested Resident Harriet Quinn Woodmoor-Pinecrest Citizens' Association Chris Reynolds Seven Oaks/Evanswood Citizens' Association Rob Richardson LabQuest Community Partnership Michele Riley Silver Spring United Methodist Church Steven Rolef Dumont Oaks Community Association Tina Slater Purple Line NOW Mel Tull The Lee Development Group Dan Wilhelm Interested Resident James Williamson Williamson Lawn and Landscaping
The US 29 BRT Phase 1 project was funded through a combination of County funding and a $10 million Federal TIGER Grant. The US 29 BRT Phase 2 preliminary engineering project (35% design) is funded through a combination of State and local funding sources. A detailed view of the project funding, budget, and additional data can be found on Montgomery County’s Capital Budget website here .