The project includes the construction of approximately 1,300 feet of eight feet wide pervious concrete bike path on the south side of Needwood Road from Redland Road to Deer Lake Road with underdrain system and varying width of grass buffer between the edge of the road and the proposed bike path. The project also includes the reconstruction of the ramps at the southeast corner of the intersection of Redland Road and Needwood Road and relocations of the two Audible Pedestrian Signal poles.
The construction started in December 2015 and ended in April 2016.
Shirley Reeves-Collette, Area Engineer Montgomery County Department of Transportation Division of Transportation Engineering 100 Edison Park Drive, 4th Floor Gaithersburg, Maryland 20878 Phone: 240-773-3412 E-mail: [email protected]
Needwood Road - Pre-construction
Verizon Pole Relocation
Clearing Ground
Construction Pervious Pavement
Storm Drain Installation
Putting down sod
Geo Matting on Slope