Washington Grove Connector - Crabbs Branch Way Extension
The Washington Grove Connector Trail project will result in a shared use path from the terminus of Brown Street in Washington Grove to the terminus of Crabbs Branch Way. The proposed 850-foot long, 10-foot wide trail will provide a paved connection for pedestrian and bicycle users from Washington Grove to destinations and transit hubs such as the Shady Grove Metro station. This important connection is identified in the 2006 Shady Grove Sector Plan and 2021 Shady Grove Sector Plan Minor Master Plan Amendment.
Project Schedule
- Selected Alternative: Q3 2024
- Mandatory Referral: Q2 2025
- 65% Design Milestone: Q3 2025
- 90% Design Milestone: Q4 2025
- Public Hearing: Q4 2025
- Final Design Complete: Q1 2026
- Construction Begins: Q2 2026
Project Documents
Project Manager
Jean Anne Kapusnick, PEMontgomery County Department of Transportation
Division of Transportation Engineering
100 Edison Park Drive, 4th Floor
Gaithersburg, MD 20878
Phone: 240-777-7240
E-mail: jean.kapusnick@montgomerycountymd.gov