Leisure World Stormwater Pond Retrofit Project

Leisure World Stormwater Project The Leisure World Stormwater Pond, originally constructed in 1982, was selected for upgrades and improvements after a 2020 inspection of the pond conducted by DEP revealed several structural issues with the dam embankment. Temporary repairs were completed later in 2020. Permenant repairs and improvements will bring the pond into compliance with current safety and performance standards reducing the impacts of stormwater runoff on our local streams and the Chesapeake Bay.

Upgrades and improvements to the stormwater management pond include: removal of accumulated sediment to reestablish the original pond bottom elevation, replace the existing riser with a new concrete riser structure, replace the corrugated metal spillway pipe with a new 48" concrete pipe, aquatic plants, trees and shrubs will be planted around the perimeter of the pond.
View more pictures of the project;

Project Details

Public Events and Project Schedule

Calendar Graphic

Design Began

August 2021

Calendar Graphic

Preliminary Assessment

January 2022

Calendar Graphic

Public Meeting

June 2022
The Greens at Leisure World Condominium Association

Calendar Graphic

Final Plans

May 2023

Calendar Graphic

Condominium Association Meeting

June 2024

Calendar Graphic

Construction

Spring - Fall 2025

*Project schedule is tentative and dates are subject to change.