Kensington Volunteer Fire Station 5, Resurfacing
Montgomery County Government
Department of General Services
Division of Building Design & Construction
Division Chief: Hamid Omidvar, AIAHamid.Omidvar@montgomerycountymd.gov
Section Chief: Randall Hawkins
Project Manager: Gary Colton
Architect / Engineer
NOA Architects, Planning & Interiors, LLCContractor
D&F ConstructionFor operations inquiries. Please contact.
Current Phase: Construction
The contractor started construction on October 18, 2023, and achieved substantial completion of all resurfacing on February 21, 2024. The punch list walk was held on February 28th. The new lower level doors have been fabricated and installation is scheduled for March 7th.
The scope of work will be to repair and resurface the parking lot and to provide ADA accessible routes of access to the public meeting room and public entrance along with required ADA parking.
Architectural and Construction Images
Architectural and Construction Images