The purpose of this project is to provide one way 5 ft to 6 ft wide separated bike lanes along Executive Boulevard from Woodglen Drive to Nicholson Lane.
Resurfacing work will begin in August 2019 and will continue into late summer or early fall. New pavement markings will be installed to implement the master planned separated bike lanes.
The first phase of construction will involve the modification of handicap ramps and new accessible pedestrian signals at the Nicholson Lane and Executive Boulevard intersection. This work will begin around August 1st through mid August.
The second phase of the project will begin on or around August 25th and will involve the repaving of Executive Boulevard in the evening hours from 8pm to 5am. Night work is being performed to minimize disturbance of traffic and parking operations. This work will be followed by the addition of lane markings, signing, and curb bike lane barriers instead of flex posts. Work is anticipated to be completed in September 2019.
Matt Johnson, A.I.C.P. Bikeways Coordinator Division of Transportation Engineering 100 Edison Park Dr., 4th Floor Gaithersburg, MD 20878 E-mail: [email protected] Phone: 240-777-7237