Judicial Center Building (JC) HVAC Renovation & Upgrade Project

Notice: Starting October 2024

Show the project location in google map 50 Maryland Avenue, Rockville MD 20850

Project Scope
The scope of this Project is a continuation of the 2016 HVAC Project. The chillers are 30 years old and the rest of the scoped auxiliary equipment to be replaced and upgraded are 47 years old.

Contact Information

Montgomery County Government
Department of General Services
Division of Facilities Management

Email Contact: [email protected]
Phone: 240-777-7777
Division Chief: Gus MontesDeOca
Section Chief: Hargurpreet Singh
Project Manager: Maurice Betaharon, Senior Mechanical Engineer
240-876-1121

Current Phase: Preparation

Project Schedule:

  • Project Start - October 1, 2024
  • Power Shut-down - December 7, 2024 to December 9, 2024
  • Project Completion - April 30, 2025