Permanent Patching Program

The Permanent Patching Program provides for deep patching of roadways to restore limited structural integrity, prolong pavement performance, and to ensure viability until rehabilitation or reconstruction can occur. Permanent Patching is accomplished with hot mix asphalt (HMA) and will yield a service of life of between 15-20 years.

2024 CONSTRUCTION SEASON:  Updated: July 26, 2024
Only in progress and upcoming projects are listed. Once a project has been completed, it is removed from the table below.  Check back periodically as projects get added or scheduled. This schedule may be changed and substitutions may be made at any time due to weather and/or operational reasons.

Roadway/Subdivision Construction Season Status
Peachtree Road Summer 2024 80%
Greenridge Acres Summer 2024 50%
Admirals Court & Way 2024/2025 0%
Oakmont Ave & Hempstead Avenue 2024/2025 0%
Purcell Drive & Court Summer 2024 0%
Conrad Spring & Branch Hill Road  Summer 2024 0%
Highland View Phase I 2024/2025 0%
Snowden Mill; 2024/2025 0%
Middlebridge 2024/2025 0%
Ednor View Terrace Summer 2024 0%
Seneca Overlook Summer 2024 0%