Sidewalk & Curb/Gutter Repair Replacement Schedule
2025 CONSTRUCTION SEASON: Updated -November 3, 2025
Click on any linked Neighborhood or Location name to read or download a Project Newsletter describing the scope of the project.
Please note: Concrete, Paving, Resurfacing and Patching programs are seasonal activities, suspended from November to March or April. Work resumes in March or April once the weather allows. Only in progress and upcoming projects are listed. Once a project has been completed, it is removed from the table below.
Check back periodically as projects get added or scheduled. This schedule may be changed and substitutions may be made at any time due to weather and/or operational reasons.
|
Neighborhood/Location |
Construction Season | Status |
|---|---|---|
| Broadbirch Drive | Summer/Fall 2025 | 100% |
| Brownstown Estates Subdivision | 100% | |
| Fernwood Phase II | Summer/Fall 2025 | 50% |
| Henderson Corner Phase II | Spring/Summer 2026 | 0% |
| Montgomery Village Ave. (Concrete) | Spring/Summer 2025 | 100% |
| Montgomery Village | Spring 2025 | 0% |
| Purple Line Station | Spring 2025 | 100% |
| Kemp Mill Estates, Ph. II Subdivision | Spring/Summer 2026 | 5% |
| Kemp Mill Estates, Ph. II Subdivision (FY25) | Spring 2025 | 100% |
| Milestone Phase II Subdivision | Spring/Summer 2026 | 0% |
| Rolling Acres Subdivision | Summer/Fall 2025 | 100% |
| Waters Landings Phase II Subdivision | Summer/Fall 2025 | 100% |
| Watkins Mill Road | Summer/Fall 2025 | 0% |
| Bushey Drive | Summer/ Fall 2025 | 100% |